The project installed a pilot sewage treatment plant to capture sludge gases, upgrade them to natural-gas quality and make them available to the public vehicle fleet as biofuel (biomethane). The services rendered within the project included process selection, siting, compilation of basic data and detailed planning, construction and commissioning of the plant as well as an aftercare phase. In addition, the project conducted accompanying training activities to ensure the plant is well-operated and maintained.

Project data

Countries
Brazil
IKI funding
2,328,059.00 €
Duration
02/2009 till 12/2017
Status
completed
Implementing organisation
Fraunhofer-Gesellschaft zur Förderung der angewandten Forschung e.V. - Institut für Grenzflächen- und Bioverfahrenstechnik
Political Partner
  • Brazilian Cooperation Agency (ABC)
Implementing Partner
  • Basic Sanitation Company of the State of São Paulo S.A. (Sabesp) - Brazil
  • DEDINI (Plant Constuction Company) - Brazil

State of implementation/results

  • Project completed.
  • The Brazilian water and waste management company owned by São Paulo state SABESP was identified as project partner, Franca in the Brazilian state of São Paulo was selected in a joint process as location of the plant.
  • Declaration of intent made by project partner to replicate the project in additional locations if it is successfully implemented.
  • Design of sewage treatment plant planned, all process stages specified, and plant components procured.
  • Documents drafted for pre-authorisation as well as installation and construction permits.
  • Gas tank and gas cleaning container shipped to Brazil and delivered at Franca.
  • Project presented at numerous events to disseminate information about the approach.
  • 10/2017 delegation trip: eight high-ranking representatives of the brazilian watersupplier SABESP were formed in Germany on the topics of sludge digestion and biogas treatment progress (among other things, the sewage treatment plants in Heidelberg and in Edenkoben were visited).

Latest Update:
12/2025

Further links

Legend:

  • Current Project
  • Previous project
  • Follow-up project
  • Topic
  • Country selection

The link has been copied to the clipboard

Related news

Barbara Waelkens from Fraunhofer IGB fuels the very first service vehicle using the biomethane acquired; Image: Fraunhofer IGB
12/28/2017

Climate friendly sludge gas treatment plant opened in Brazil